TABLE OF CONTENTS

 

Executive Summary   1

1.       INTRODUCTION   2

2.       AIR QUALITY   5

3.       NOISE   7

4.       LANDSCAPE AND VISUAL   9

5.       WASTE MANAGEMENT   10

6.       SITE INSPECTION   11

7.       ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE   12

8.       IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION MEASURES   13

9.       FUTURE KEY ISSUES   14

10.     Conclusions   15

 

 

FIGURES

 

Figure 1                 Project General Layout

Figure 2                 Air and Noise Monitoring Locations

 

 

LIST OF APPENDICES

 

Appendix A

Project Organization Chart

Appendix B

Event Action Plans

Appendix C

Waste Flow Table

Appendix D

Environmental Mitigation Implementation Schedule (EMIS)

Appendix E

Weather and Meteorological Conditions during Reporting Month

Appendix F

Cumulative statistics on Environmental Complaints, Notifications of Summons and Successful Prosecutions

Appendix G

Summary of Site Audit in the Reporting Month

Appendix H

Outstanding Issues and Deficiencies

Appendix I

Action and Limit Levels for Air Quality and Noise

 

 

 


Executive Summary

 

 i.   The Civil Engineering and Development Department HKSAR has appointed MateriaLab Consultants Limited (MCL) to undertake the Environmental Team services for the Project and implement the EM&A works.

 

ii.   This Monthly EM&A report presents the environmental monitoring and audit works for the period between 1 March and 18 March 2021. As informed by the Contractor, no major construction activities were carried out in the reporting month.

 

Breaches of the Action and Limit Levels

 

iii.       No Action / Limit Level exceedance was recorded for 24-hr TSP at KTD1, KTD2c and KER1 in the reporting month.

 

iv.   No Action / Limit Level exceedance was recorded for construction noise at KTD1, KTD2c and KER1 in the reporting month.

 

Complaint, Notification of Summons and Successful Prosecution

 

v.   No environmental complaint, notification of summons and successful prosecution were received in the reporting month.

 

Reporting Changes

 

vi.   The proposal for Termination of EM&A Programme under this Contract was certified by the ET Leader, verified by the IEC on 15 December 2020, approved by EPD on 18 March 2021. The construction phase of EM&A programme has been terminated on 18 March 2021.

 

Future Key Issues

 

vii.   There was no future key issues in the reporting month.